![]() |
Emergency |
|
| Your location: Rideau Region > Rideau Waterway > Behind the Scenes > Emergency Repairs |
| While regular maintenance of the Rideau Canal prevents many problems, unexpected problems do occur. In 2005 the Clowes lock and the Ottawa locks had to be briefly shut down for emergency repairs. Time is of the essence to get the canal back in operation and the engineering teams scrambled to identify the problem and implement a solution. In both cases it was a job well and quickly done. This is their story: |
||||||||||||||||||||||||||||
| Clowes Lock Repair by Bill Pratt - Asset Management and Construction Engineer, Rideau Canal Thought I would take a little time and inform you all of the events that occurred at Clowes Lockstation last week. Tuesday [July 5, 2005], late in the morning, Gerald Covell phoned Rideau Engineering identifying a serious "muddy boil" downstream of their Lower Gates. The water flow feeding the "boil" made operation of the Upper Gates extremely difficult. Upon inspection, Engineering immediately called in a dive team in the hopes of finding an entrance hole in, or near, the upstream side of the Gate Sill. Kanata Diving arrived at the site within two hours but were unable to find any sizeable void. That evening it was decided that, even though it was July, Clowes would have to be closed and Dewatered.
Thursday 7:00 am, our own Luc Beriault of PWGSC was called in to design new anchors to stabilize the Sill against further lifting; Shops re-established as best they could the metal plates on top of the existing anchors and; Engineering hustled to find new anchors that hopefully could be delivered and installed the following day and, with Shops & Central Sector Crews, pumped grout into the voids in the stone, mortar and concrete components of the Sill. The operation finished around 8:00 pm. Friday 7:00 am, Capital Cutting and Coring of Ottawa along with Shops and Sector Staff cored the holes for the new Sill anchors; the anchors arrived from London, Ontario (overnight delivery) and were installed, post-tensioned and grouted by 7:00 pm. Clowes Lower Reach was partially raised during the night in preparation for Navigation Saturday morning. The Lock was kept Dewatered overnight to allow the grout to set up.
Saturday 6:00 am, Shops and Sector Crews arrived on site in the rain to flood the Lock. Unfortunately, the raising of the Lower Reach overnight also inadvertently raised the water in the Lock and Crews had to work in rain and waist deep water to remove sand bags and pumps from the Lock. At around 9:50 am the Lower Reach was back to Navigation levels and the Lock was reopened.
While Staff were dealing with the technical issues at Clowes, other Rideau Canal Staff were dealing with Visitor issues. Examples were: Boaters were chauffeured to town by Lock and Woods Mill Staff, one child who had an allergic reaction to peanuts was rushed to the emergency ward in Kemptville, some boaters were provided with temporary power supply. Projects like this aren't accomplished by everyone just doing their job, it takes an extraordinary effort. Congratulations to all. Last week was our chance to shine - and we did. It was good working with you. Thanks for your efforts. Bill Pratt Ottawa Locks Repair by Joe Brown, Chief Engineer, Rideau Canal Again we have had to call upon the troops to save the day. Rideau Canal employees have come together to complete an emergency repair on a gate sill at Ottawa Locks in record time.
Magically, a 10-foot long piece of plastic pipe with a large funnel secured to one end suddenly appeared on the site. Our maintenance guys had done it again. Using this device, we could now pour the thick grout down into the holes and be assured that the holes were full of grout before placing the anchor rods. Due to the failure of a number of the mechanical anchors, we would now have to depend solely upon the grout for these anchors to be effective. As it turned out we were able to set and torque over half of the anchors. The grout was given 38 hours to develop strength and the locks were open to navigation first thing Monday morning. On Wednesday, the elevation of the sill was surveyed both with full hydrostatic load and no load. No deflection was found indicating the anchors are holding. We will continue to monitor the sill periodically to the end of the current navigation season. We are now working on plans to reconstruct the sill after navigation this year. I would like to thank everyone involved in this project for their hard work, valuable input and cooperation. Everyone was super. Joe Brown Chief Engineer, Rideau Canal
|
||||||||||||||||||||||||||||